Identify the missing word(s) in the following sentence. During a quality review meeting [ ? ] any identified defects.
Suggested Answer: C Vote an answer
During a quality review meeting in PRINCE2, it is critical that any agreed actions for identified defects are recorded. This ensures that there is clarity on what is to be done, by whom, and by when, to address these defects. References: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.