Exam PRINCE2-Foundation Topic 1 Question 469 Discussion

Actual exam question for PRINCE2's PRINCE2-Foundation exam
Question #: 469
Topic #: 1
Which process defines the work to deliver the major products ensuring that an organization uses its resources effectively?

Suggested Answer: D Vote an answer

The 'managing product delivery' process in PRINCE2 defines the work needed to deliver major products, ensuring effective use of organizational resources. This process focuses on the acceptance, execution, and delivery of project products according to agreed plans between the project manager and the team manager.
References: PRINCE27 Foundation guide on the 'managing product delivery' process.

by Simon at Aug 20, 2026, 09:17 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.