Exam ISO-45001-Lead-Auditor Topic 6 Question 66 Discussion
Actual exam question for PECB's ISO-45001-Lead-Auditor exam
Question #: 66
Topic #: 6
Question #: 66
Topic #: 6
Showitoff is an organization specialization in the design and production of wall decorating materials for the domestic market.
During an ISO 45001 certification audit of the site, the auditor comes across an open, walled area just outside the maintenance department. It contains various scraps of wood and metal as well as serveral rusty components. Several heavy concrete beams are learning against a thin brick wall in which cracks are available. When asked about it, the OHS Manager states that he presumes that the materials come from maintenance work, so it is the Maintenance Manager's responsibility.
The auditor interview the Maintenance Manager in his department. He asks about the area outside and is told that it contains some excess material that the Manager likes to keep in case they come in handy at some stage. The auditor points out that the wall appears to be unstable and could collapse at any moment. The Maintenance Manager is not aware of such a situation.
Wash-it-up is an organization that provides window cleaning services for the industrial sector. It has been certified to ISO 45001 for some time and has appointed a new OHS Manager. The auditor asks to see the most recent management review meeting minutes.
Which three statement would represent input audit evidence for the management review?
During an ISO 45001 certification audit of the site, the auditor comes across an open, walled area just outside the maintenance department. It contains various scraps of wood and metal as well as serveral rusty components. Several heavy concrete beams are learning against a thin brick wall in which cracks are available. When asked about it, the OHS Manager states that he presumes that the materials come from maintenance work, so it is the Maintenance Manager's responsibility.
The auditor interview the Maintenance Manager in his department. He asks about the area outside and is told that it contains some excess material that the Manager likes to keep in case they come in handy at some stage. The auditor points out that the wall appears to be unstable and could collapse at any moment. The Maintenance Manager is not aware of such a situation.
Wash-it-up is an organization that provides window cleaning services for the industrial sector. It has been certified to ISO 45001 for some time and has appointed a new OHS Manager. The auditor asks to see the most recent management review meeting minutes.
Which three statement would represent input audit evidence for the management review?
Suggested Answer: F,G,H Vote an answer
Comprehensive Detailed Explanation along with All ISO 45001 Audit Reference Clause 9.3 of ISO 45001:2018 defines inputs for management review, which must include information on performance trends, feedback, risks, and opportunities for improvement.
Analysis of Options:
A . Allocation of a bigger budget for the OHS department:
This is an output of management review, not an input.
B . Decisions on improvements in the OHSMS:
This is an output, not an input.
C . Decisions related to continual improvement opportunities:
This is an output, not an input.
D . Procurement of new safety harnesses for workers:
This is an operational action, not an input for management review.
E . Proposal to prioritize health and safety issues as a business strategy:
Proposals may be discussed during review, but they are outputs.
F . Report showing the trend of an increase in safety incidents:
Correct. This is a valid input that informs system performance.
G . Updates to the risk register:
Correct. Risk updates are required inputs under Clause 6.1.2.
H . Worker feedback of positive and negative comments:
Correct. Feedback is an essential input per Clause 5.4 and Clause 9.3.
ISO Reference:
Clause 9.3: Management review inputs.
Clause 5.4: Worker consultation and participation.
Analysis of Options:
A . Allocation of a bigger budget for the OHS department:
This is an output of management review, not an input.
B . Decisions on improvements in the OHSMS:
This is an output, not an input.
C . Decisions related to continual improvement opportunities:
This is an output, not an input.
D . Procurement of new safety harnesses for workers:
This is an operational action, not an input for management review.
E . Proposal to prioritize health and safety issues as a business strategy:
Proposals may be discussed during review, but they are outputs.
F . Report showing the trend of an increase in safety incidents:
Correct. This is a valid input that informs system performance.
G . Updates to the risk register:
Correct. Risk updates are required inputs under Clause 6.1.2.
H . Worker feedback of positive and negative comments:
Correct. Feedback is an essential input per Clause 5.4 and Clause 9.3.
ISO Reference:
Clause 9.3: Management review inputs.
Clause 5.4: Worker consultation and participation.
by Susie at Apr 13, 2026, 07:06 PM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).