You are an administrator who uses Project Server 2013 and Project Professional 2013.
The leadership of your organization asks you to assign resources to teams so that the resources are aligned with a team definition.
You need to implement this request.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
Correct Answer: C,D Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
You are a Project Server 2013 administrator, and you support the Project Management Office (PMO) project managers who need to estimate project hours and costs without knowing the specific resource names.
There are options available to accommodate this request when creating resources on Project Server 2013.
You need to allow project managers to plan workload and cost from the task level up.
What should you do?
Correct Answer: A Vote an answer
You work for a multinational corporation which uses Project Server 2013 to plan and control the projects in different business units. Each business unit has its own portfolio of projects but can participate in strategic projects. The Project Management Office (PMO) configures as many Enterprise Project Types as necessary to create new products, launch marketing campaigns, and deploy new lines of business tools to comply with the governance processes.
A business unit creates a new proposal, and your team waits for the new proposal approval, which will provide the information necessary to begin this proposal. In the Project Center, the stakeholders are able to view the phases and stages of each proposal, and your proposal has not moved since the last time you saved it in Project Web App (PWA). The sponsor waits for the notification to review and authorize the next stage of the project.
You need to ensure the project moves through its lifecycle.
What should you do first?
Correct Answer: D Vote an answer
Your organization is using Project Online to facilitate the selection of optimal portfolios.
The Project Management Office (PMO) expects to analyze the portfolio of projects in a short period of time by using the efficient frontier and the strategic value provided by the tool.
You need to ensure the tool provides the expected outcome.
Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)
Correct Answer: A,B,C Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
HOTSPOT
A company has established these three business drivers for a Portfolio Analysis:
1.Improve Customer Satisfaction
2.Increase Market Share
3.Standardize Processes
The board of directors plans to perform a pairwise comparison to prioritize the business drivers.
After the board of directors sets two out of the three priorities, you realize you can finish the job.
You need to ensure that the consistency ratio of the final outcome is 100%.
What should you do? (To answer, configure the appropriate option in the dialog box in the answer area.)
Correct Answer:
You are in the Project Management Office (PMO) for a company that uses Project Online to select portfolios for each business unit.
The parameters used as cost constraints vary from department to department, including Cost, CapEx, and Estimated Hours. You are responsible for providing the infrastructure to support the various constraints.
You need to select a feasible method for employing cost constraints.
Which two fields should you use? (Each correct answer presents part of the solution. Choose two.)
Correct Answer: A,D Vote an answer
You are a project manager for an organization that uses Project Online.
You create a resource plan to provide high level resource demand during the portfolio intake and selection process.
Your project is now selected for detailed planning. You complete a detailed work breakdown structure (WBS).
You need to remove the resource demand from the resource plan.
What should you do?
Correct Answer: C Vote an answer
You are a project manager who uses Project Server 2013.
You have an in-progress project. A resource who has reported actual work on the project is no longer available. You want to preserve their actual work.
You need to replace this resource with a newly-hired resource.
What should you do?
Correct Answer: C Vote an answer
You are a project manager who uses Project Server 2013 and Project Professional 2013.
You are managing a project that has already begun. A new change request has been pre-approved, and the director wants to understand the impact to the overall project schedule prior to formally approving the project to include in the project schedule.
You add the change request to your project schedule. Your original baseline is Baseline1.
You need to include the change request in your baseline to see the impact of your overall project schedule including duration, work, and cost.
What should you do?
Correct Answer: C Vote an answer
Your company uses Project Server 2013 to evaluate and select projects based on a primary cost constraint, as well as a secondary constraint of internal rate of return (IRR).
Management authorizes a budget and establishes a minimal IRR of 5% to execute any project the following year. Your company has never analyzed constraints other than cost.
As the portfolio analysis expert, you need to recommend a reasonable approach to perform the analysis.
What should you recommend?
Correct Answer: C Vote an answer