Exam P3 Topic 1 Question 104 Discussion

Actual exam question for CIMA's P3 exam
Question #: 104
Topic #: 1
A project has a net present value of $2 million.
Total cash outflows of this project have a present value of $14 million, which includes staff costs of $10 million.
What is the project's sensitivity to staff costs?

Suggested Answer: C Vote an answer

by Jack at Aug 24, 2026, 04:43 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10