A project has a net present value of $2 million.
Total cash outflows of this project have a present value of $14 million, which includes staff costs of $10 million.
What is the project's sensitivity to staff costs?
Total cash outflows of this project have a present value of $14 million, which includes staff costs of $10 million.
What is the project's sensitivity to staff costs?
Suggested Answer: C Vote an answer