Exam P3 Topic 1 Question 285 Discussion

Actual exam question for CIMA's P3 exam
Question #: 285
Topic #: 1
YGH has recently completed a post completion audit on a five year contract that has only recently come to a conclusion. The main finding was that the project delivered most of the expected benefits, but that it cost significantly more to implement than had been anticipated at the project appraisal stage. YGH would not have proceeded if the true cost had been known at that stage.
The project was the responsibility of the production department, which is presently managed by G.
When the project was proposed, the production department was managed by H.
H is now YGH's Director of Operations.
How should the finding from this post completion audit be interpreted?

Suggested Answer: A Vote an answer

Explanation
Calculation_F0

by Heather at Jul 25, 2026, 12:31 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10