Free APD01 Questions for Blue Prism Accredited Professional Developer APD01 Exam as PDF & Practice Test Engine

  • Exam Code/Number: APD01
  • Exam Name/Title: Blue Prism Accredited Professional Developer Exam
  • Certification Provider: Blue Prism
  • Corresponding Certification: Blue Prism Certification
  • Exam Questions: 52
  • Updated On: Jun 21, 2026
Which of the following are correct? (Choose three.)
Correct Answer: A,C,D Vote an answer
Which of the following statements about the status of a work queue is/are correct?
1. The status can be used as a method of recording what work has been done so far on a Work Queue item
2. The status is set using the Update Status action of the Work Queues business object
3. Every time the Update Status action is executed, the existing status is appended. Each status is separated with a semi colon.
4. The status can be used to aid manual working of exceptions; providing the Item Status can inform staff what work is still outstanding on an item that needs manually completing
Correct Answer: C Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
A retail bank has promoted 5 Blue Prism processes to production:
Email Poller
Customer Onboarding
Amend Contact Details
Direct Debit Cancellations
Onboarding Reporting
One instance of the email Poller process will run 24/7 feeding work queues for the other two processes.
Two concurrent instances of the Customer Onboarding process will run between 6am and 11pm each day on the same VM.
Two concurrent instances of the Amend Contact Details process will run between 8am and 8pm each day on two VMs.
One instance of the Direct Debit Cancellations process will run between 6am and 4pm each day on the same VM as the Email Poller process. The scheduler that starts the Direct Debit Cancellations process is configured to run the Onboarding Reporting process when the Direct Debit Cancellations process has successfully completed.
How many robot licenses are required?
Correct Answer: B Vote an answer
A Process Definition Document, for a new process to open ISA accounts, specifies that the value "2008 Cash ISA" is to be entered into the Product Selection field of the following screen:

The Product Selection field is a drop down menu with the following options available:

According to Best Practice, which of the following design options are correct for populating the Product Selection field with the value 2008 Cash ISA:
Correct Answer: A Vote an answer
When using Surface Automation which of the following Navigate Stage Actions should be used to press a button which has been identified as a Region?
Correct Answer: C Vote an answer
An Insurance company has created 4 Blue Prism processes:
Change of Address
Claims Processing
Renewals
Order Letter
The Order Letter process is not a published process but is called as a sub process by each of the 3 other processes.
Each day at 6am a scheduler starts:
2 instances of the Renewals process on the same virtual machine
9 instances of the Claims Processing process on 3 different virtual machines
1 instance of the Change of Address process on its own virtual machine
How many robot licenses will be consumed by the running processes?
Correct Answer: A Vote an answer
0
0
0
10