An administrator is preparing to create a new workload domain within an existing VCF instance.
Which two tasks must be completed before starting the deployment workflow? (Choose two.)
Which two tasks must be completed before starting the deployment workflow? (Choose two.)
Suggested Answer: B,D Vote an answer
All ESXi hosts must be installed with a supported ESXi version using a VMware ISO before they are commissioned into SDDC Manager. Commissioning is always performed via the management domain vCenter.