An Operations Engineer is preparing to convert a standard 4-node VI Workload Domain cluster into a vSAN Stretched Cluster using the SDDC Manager automated workflow.
```
[SDDC Manager - Stretch Cluster Wizard]
Source Cluster: WLD01-Cluster01 (4 Hosts)
Target Expansion: Add 4 Hosts to Site B.
```
What is a mandatory procedural prerequisite that the engineer must complete *before* SDDC Manager allows the "Stretch Cluster" workflow to successfully execute?

Suggested Answer: A Vote an answer

by Roy at May 04, 2026, 01:05 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10