Exam 2V0-13.25 Topic 4 Question 46 Discussion

Actual exam question for VMware's 2V0-13.25 exam
Question #: 46
Topic #: 4
An organization is evacuating their current datacenter and moving all workloads to a new datacenter. The organization has a total of 800 workloads to move, and the migration must be completed with no downtime within a planned change window that is scheduled to occur in four weeks.
What migration method will meet the requirements?

Suggested Answer: D Vote an answer

The requirements specify:
* Large-scale migration (800 workloads).
* No downtime.
* Strict change window (4 weeks).
HCX Replication Assisted vMotion (RAV) is the only method that combines large-scale migration efficiency with zero downtime:
* Workloads are replicated in advance.
* During the cutover, a vMotion-like switchover completes with no outage.
Other methods:
* Cross vCenter vMotion works for live moves but is not efficient for hundreds of VMs within a short timeline.
* HCX OS Assisted Migration is for physical-to-virtual or non-vSphere workloads (not applicable).
* HCX Bulk Migration is efficient but introduces downtime during cutover.
Thus, HCX RAV best meets the no-downtime, large-scale requirement.
Reference: VMware HCX Migration Guide - Replication Assisted vMotion Use Cases.

by Tony at Oct 29, 2025, 04:34 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10