True or False: Product Owners must specify complete acceptance criteria for a Product Backlog item before the Developers can select the item in Sprint Planning.
Correct Answer: A Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
What are three advantages of a Product Owner sharing a clearly defined Product Goal with the Scrum Team?
(choose the best three answers)
Correct Answer: B,C,D Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
Who is accountable for tracking the remaining work toward the Sprint Goal?
(choose the best answer)
Correct Answer: C Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
What are the two primary ways a Scrum Master helps a Scrum Team work at its highest level of productivity?
(choose the best two answers)
Correct Answer: A,B Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
What tactic should a Scrum Team use to divide a group of 100 people into multiple Scrum Teams?
(choose the best answer)
Correct Answer: A Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
What enhances the transparency of an Increment?
(choose the best answer)
Correct Answer: B Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
When does a Sprint conclude?
(choose the best answer)
Correct Answer: B Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
Which statement best describes Scrum?
(choose the best answer)
Correct Answer: C Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
At the end of a Sprint, a Product Backlog item worked on during the Sprint does not meet the Definition of Done. What two things should happen with the undone Product Backlog item?
(choose the best two answers)
Correct Answer: A,D Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
A new Developer is having continuing conflicts with existing members of the Scrum Team, which is impacting the delivery of the Increment. If necessary, who is responsible for removing the Developer from the Scrum Team?
(choose the best answer)
Correct Answer: C Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
When should a Sprint Goal be created?
(choose the best answer)
Correct Answer: A Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
A Sprint Retrospective should be held:
(choose the best answer)
Correct Answer: B Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
Who is accountable for creating a valuable and usable Increment each Sprint?
(choose the best answer)
Correct Answer: B Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
The IT manager asks a Scrum Team for a status report describing the progress throughout the Sprint. The Scrum Team asks the Scrum Master for advice. The Scrum Master should:
(choose the best answer)
Correct Answer: E Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).