Who collaborates on understanding the work of the Sprint?
Suggested Answer: A Vote an answer
The entireScrum Teamcollaborates on understanding the work of the Sprint duringSprint Planning. This includes theProduct Owner,Developers, andScrum Master. Each role has a contribution:
* Product Owner:Explains the Product Backlog items, priorities, and their value.
* Developers:Collaborate to create a plan for delivering the selected Product Backlog itemsand achieving the Sprint Goal.
* Scrum Master:Facilitates the discussion to ensure alignment and understanding but does not directly plan the work.
According to the2020 Scrum Guide:
* "Sprint Planning initiates the Sprint by laying out the work to be performed for the Sprint. This resulting plan is created by the collaborative work of the entire Scrum Team." Why the other options are incorrect:
* B. The Scrum Master and the Developers:This excludes the Product Owner, who is essential for providing clarity and prioritization of Product Backlog items.
* C. The Product Owner and the Developers:While they collaborate during Sprint Planning, the Scrum Master also plays an important role in facilitating the discussion.
* D. The Developers:The Developers alone cannot decide on the Sprint Goal or select work without input from the Product Owner.
* Product Owner:Explains the Product Backlog items, priorities, and their value.
* Developers:Collaborate to create a plan for delivering the selected Product Backlog itemsand achieving the Sprint Goal.
* Scrum Master:Facilitates the discussion to ensure alignment and understanding but does not directly plan the work.
According to the2020 Scrum Guide:
* "Sprint Planning initiates the Sprint by laying out the work to be performed for the Sprint. This resulting plan is created by the collaborative work of the entire Scrum Team." Why the other options are incorrect:
* B. The Scrum Master and the Developers:This excludes the Product Owner, who is essential for providing clarity and prioritization of Product Backlog items.
* C. The Product Owner and the Developers:While they collaborate during Sprint Planning, the Scrum Master also plays an important role in facilitating the discussion.
* D. The Developers:The Developers alone cannot decide on the Sprint Goal or select work without input from the Product Owner.
by Howar at Apr 27, 2025, 12:06 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).