What are two ways program risks can be categorized? (Choose two.)
Suggested Answer: C,E Vote an answer
Program risks can be categorized based on whether they are Deferred or Owned. A deferred risk is one that has been identified but is not being actively addressed at the moment, possibly due to prioritization of other risks or resource constraints. An owned risk is one that has been assigned to an individual or team who is responsible for managing and mitigating the risk. This categorization helps in tracking and accountability within the SAFe framework.
by patilmalti121262 at Jan 07, 2025, 10:02 AM
0
0
0
10
Comments
patilmalti121262
2025-01-07 10:02:34Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).