Your production planners are supposed to execute planning only for specific resources. What do you use to achieve this in Advanced Planning (PP/DS)?
Correct Answer: C Vote an answer
Your company manufactures materials whose characteristics differ for each manufacturing process.
Which application do you choose in SAP S/4HANA to track and use this information in all areas of logistics?
Correct Answer: A Vote an answer
What determines whether the planned independent requirements in demand management are consumed by other requirements? Note: There are 2 correct answers to this question.
Correct Answer: A,B Vote an answer
Under what circumstances can you change the material type for a material if stocks, reservations, or purchasing documents exist? Note: There are 2 correct answers to this question.
Correct Answer: A,C Vote an answer
When do you use variant bills of material (BOMs)?
Correct Answer: B Vote an answer
You want to trigger in-house production of a semi-finished material before a sales order for the corresponding finished good is received.
Which planning strategy supports the consumption of planned independent requirements by dependent requirements for the semi-finished material?
Correct Answer: D Vote an answer
In SAP documentation for MRP in Advanced Planning, you read that the MRP creates new planned orders through infinite scheduling. What does this mean for the capacity requirements of the new planned order?
Correct Answer: B Vote an answer
In which master data objects do you maintain data to determine the duration of an operation for production?
Note: There are 2 correct answers to this question.
Correct Answer: C,D Vote an answer
Which of the following are scheduling time elements for a production order?
Note: There are 3 correct answers to this question.
Correct Answer: A,B,E Vote an answer