Exam PRINCE2Foundation Topic 1 Question 312 Discussion

Actual exam question for PRINCE2's PRINCE2Foundation exam
Question #: 312
Topic #: 1
Where should decisions regarding the tailoring of the project be recorded?

Suggested Answer: C Vote an answer

by Christ at Sep 22, 2026, 05:33 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10