You are managing a portfolio in a functional organization and resources are shared between operations and projects. You are continuously performing capability and capacity analysis in order to optimize the portfolio. Which of the following capability and capacity analysis is used to limit the number AND size of components the organization can execute?
Correct Answer: B
Vote an answer
Assume you are the portfolio manager for a company that specializes in software, including portfolio management software. It has many components under way to enhance the existing product line but also to move the company into Cloud computing. You regularly prepare reports on the portfolio status but lately have had a large number of stakeholders request ad hoc reports.
You decided to survey your stakeholders to learn about their information needs. You next decided to hold some one- on-one interviews with several interested and influential stakeholders in terms of communications requirements. From these interviews you are concerned that some stakeholder groups may be missing so you decided to:
You decided to survey your stakeholders to learn about their information needs. You next decided to hold some one- on-one interviews with several interested and influential stakeholders in terms of communications requirements. From these interviews you are concerned that some stakeholder groups may be missing so you decided to:
Correct Answer: B
Vote an answer
Developing the Portfolio Management Plan is a major step in a Portfolio and for a Portfolio Manager. You are currently developing this plan and having focus groups and brainstorming activities during which you are using mind-maps diagrams to organize the idea into logical groupings. Which of the below are you using?
Correct Answer: A
Vote an answer
The portfolio is undergoing and your are now in the monitoring and controlling phase. Two of your team members are arguing about what to use in order to determine decisions to be made with regards to the portfolio and its components. What should be your advice to them?
Correct Answer: B
Vote an answer
Efficiency is highly regarded when managing a portfolio and spans all activities i.e. risk management, communication management, etc. A portfolio is considered efficient if it
Correct Answer: A
Vote an answer
An optimal portfolio based on Modern Portfolio Theory would:
Correct Answer: B
Vote an answer
In your web app company, the portfolio is constantly changing. It is not unusual for a new proposal to be submitted each day and for other components to be terminated as a competitor was first to market. The Portfolio Review Board usually meets daily in this fast-paced environment as it:
Correct Answer: D
Vote an answer
Managing risk is key to the success of any initiative. Risk is considered to be inherent in any activity we do in project management and at any level. Risk is incorporated in all process groups as well. As a portfolio manager, how do you map the risk management elements to process groups?
Correct Answer: C
Vote an answer
While managing a program for the banking sector spanning multiple transformational areas. A new portfolio manager comes to you seeking advice on the usefulness of ROI. You tell her that ROI is the best method to measure returns of
Correct Answer: D
Vote an answer
Component portfolio management stage-gate reviews are intended for the steering committee to:
Correct Answer: C
Vote an answer
A portfolio sponsor has asked the portfolio manager to include an important project in the portfolio. Which type of analysis should the portfolio manager perform first?
Correct Answer: B
Vote an answer
Each year, you update the portfolio roadmap so people within the organization can see component status, interdependencies, constraints, and business value, among other things. This year, however, two major programs in the portfolio were cancelled as they were government contracts, and the government lacked funds to complete them. Your management then had to reduce staffing. These two programs had dependencies with other components in the portfolio.
This means that:
This means that:
Correct Answer: C
Vote an answer