Free PMP Questions for PMI PMP - Project Management Professional (2026) PMP Exam as PDF & Practice Test Engine
A project is about to start with a global project team. Travel is not a viable option for project team members, so most will participate virtually.
What should the project manager do to engage the team?
What should the project manager do to engage the team?
Correct Answer: C
Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
Contract terms used during the tender phase for a new power-generation facility must be revised before signing with the successful bidder because the terms of the tender have been amended to accommodate the new financial regulations on company tax. Which approach should the project manager take to implement this amendment?
Correct Answer: C
Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
A project manager is reviewing the status of a large project with team members in different countries.
Through the status review, the project
manager notices that one team is consistently behind schedule and their work often needs to be corrected.
What should the project manager do to improve the quality of this team ' s work?
Through the status review, the project
manager notices that one team is consistently behind schedule and their work often needs to be corrected.
What should the project manager do to improve the quality of this team ' s work?
Correct Answer: B
Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
A few developers have submitted their resignation after completing their annual review and receiving their annual bonus. The project manager cannot find replacements for all of the developers in time to meet the project ' s deadline.
What should the project manager do?
What should the project manager do?
Correct Answer: A
Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
A major issue regarding conflicting priorities has been highlighted by the project team with respect to a few stakeholder requirements.
What should the project manager do?
What should the project manager do?
Correct Answer: A
Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
local company is developing a new product and. for the first time, using a remote team for the programming tasks of features. The design for the product comes from the local team. During the third sprint review, the product owner has concerns about the project ' s outcomes. The remote development team is complaining that they do not clearly understand the requirements conveyed in the daily standup meetings.
How should the project manager address this situation?
How should the project manager address this situation?
Correct Answer: D
Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
A major national company known for quality products has just selected a small subcontracting firm to assist with a project. The project manager from the subcontracting firm is meeting with the project team to ensure that the project is delivered according to the customer ' s standards in order to ensure this, what should the project manager define and document?
Correct Answer: D
Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
While an iteration is in progress, a project manager notices a delay in the prototype. The sponsor reaches out to the project manager and suggests engaging with cross-functional stakeholders.
What should the project manager do?
What should the project manager do?
Correct Answer: C
Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
A company is working on a project and is using a hybrid approach to streamline a customer service process.
At the end of the second iteration, a business analyst joins the team to learn about the financial and scheduling aspects of project management.
What should the project manager do to support the business analyst?
At the end of the second iteration, a business analyst joins the team to learn about the financial and scheduling aspects of project management.
What should the project manager do to support the business analyst?
Correct Answer: C
Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
0
0
0
10
