A risk manager wants to determine what risk has the biggest impact on project cost. The risk manager identified three risks, which could occur in different phases of the project.
What should the risk manager do first to understand the impact on project cost?
Correct Answer: C Vote an answer
During a project team meeting, a risk manager realizes that the initial assumptions on the project schedule are too optimistic. The risk manager believes that the project might not meet its deadline as initially stated.
What is the reason for misunderstanding the assumptions from the beginning?
Correct Answer: C Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
A project team successfully implemented a risk response plan for a major risk event. Residual risks were evaluated and actions were taken to keep them under control. There were no secondary risks after the implementation.
What should the risk manager do?
Correct Answer: A Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
Upon reviewing the risk analysis results, the project manager notices several risks that occur more frequently than others. What should the project manager do?
Correct Answer: A Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
A new vice president in one of its divisions observed that the portfolio of projects within their division experienced significant variations beyond the ±10% established threshold with the potential of not achieving its overall business goals. Hence, they directed all project leaders and sponsors to ensure that they set and work toward more stringent thresholds of ±5% and reports on the basis of any variance outside that range.
How should the risk manager respond?
Correct Answer: D Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
A project manager has requested a risk manager facilitate risk identification on a project. While facilitating this effort, the project manager wants to ensure that stakeholders interact and provide their expertise so that an exhaustive list of risks is created.
Which risk identification technique should the risk manager use?
Correct Answer: A Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
A project team identifies that there is a probability of missing a key milestone in a project. The team wants to move forward with the risk response planning.
What should the risk manager complete first?
Correct Answer: C Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
Several key stakeholders approach the project manager with concerns. The stakeholders have received feedback from local businesses that have reported a reduction in customers because of construction activities at the worksite, and they plan to submit a claim to the municipality to fine the project manager ' s company.
How should the project manager address this concern?
Correct Answer: D Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
The project manager leading a company ' s digital signature initiative for engineering drawings has identified threats and opportunities using a strengths, weaknesses, opportunities, and threats (SWOT) analysis.
What are two potential threats or opportunities under the SWOT analysis? (Choose two.)
Correct Answer: C,E Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
One project in a program needs to be completed in 6 months because there is a large bonus for early completion. Consequently, the program manager transfers all resources to this project and arranges for employees to receive overtime pay.
Which risk response strategy is the program manager using in this scenario?
Correct Answer: B Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
During a meeting to develop the risk management plan, the risk manager recognizes that risks may be identified that could also impact other projects that the company is pursuing. What should the risk manager do?
Correct Answer: C Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
A project lihat was in the execution phase for the last six months was put on hold and was eventually cancelled after numerous scope related challenges. It was decided to re-plan the scope and divide the project into multiple projects to have better insight into end objectives. As part of the project start up. the project manager is developing the risk planning for the project.
What three artifacts should the project manager consult or review during this process? (Choose three.)
Correct Answer: C,D,E Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
A project manager of an IT company is assigned to a project whose schedule may be delayed due to a lack of resources to conclude the backlog activities. The project manager decides to hire additional developers to reduce the project ' s technical debt and meet the project deadline.
What should the risk manager advise the project manager to do to address this situation?
Correct Answer: B Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).