Exam CAPM Topic 2 Question 211 Discussion

Actual exam question for PMI's CAPM exam
Question #: 211
Topic #: 2
What document gathers all of the lessons learned at the end of a phase or project

Suggested Answer: D Vote an answer

by daccache.anthony at Mar 06, 2026, 01:13 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
daccache.anthony
2026-03-06 01:13:39
Selected Answer: B
The correct answer is:

✅ B. Lessons learned register

Explanation

The Lessons Learned Register is the official document used to:

Collect and record lessons learned during the project or phase

Include successes, failures, challenges, and best practices

Serve as a reference for future projects to improve processes and avoid repeated mistakes

Why the other options are incorrect

A. Lessons learned project asset – Not a standard term; assets may store the register but this is not the document itself.

C. Lessons learned list – Informal term; the formal document is the register.

D. Lessons learned repository – Could be a database or system, but the register is the document that formally collects the lessons.
upvoted 1 times
...
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.