Exam CAPM Topic 2 Question 211 Discussion
Actual exam question for PMI's CAPM exam
Question #: 211
Topic #: 2
Question #: 211
Topic #: 2
What document gathers all of the lessons learned at the end of a phase or project
Suggested Answer: D Vote an answer
by daccache.anthony at Mar 06, 2026, 01:13 AM
0
0
0
10
Comments
daccache.anthony
2026-03-06 01:13:39✅ B. Lessons learned register
Explanation
The Lessons Learned Register is the official document used to:
Collect and record lessons learned during the project or phase
Include successes, failures, challenges, and best practices
Serve as a reference for future projects to improve processes and avoid repeated mistakes
Why the other options are incorrect
A. Lessons learned project asset – Not a standard term; assets may store the register but this is not the document itself.
C. Lessons learned list – Informal term; the formal document is the register.
D. Lessons learned repository – Could be a database or system, but the register is the document that formally collects the lessons.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).