Exam CAPM Topic 1 Question 457 Discussion

Actual exam question for PMI's CAPM exam
Question #: 457
Topic #: 1
Which of the following is used as an input to prepare a cost management plan?

Suggested Answer: A Vote an answer

by daccache.anthony at Mar 06, 2026, 01:08 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
daccache.anthony
2026-03-06 01:08:10
Selected Answer: B
The correct answer is:

✅ B. Expert judgment

Explanation

When preparing a Cost Management Plan, one of the key inputs is expert judgment.

Experts provide knowledge and experience on estimating, budgeting, cost control methods, and applicable standards.

This input helps define:

How costs will be planned, structured, and controlled

Units of measure, accuracy levels, and reporting formats

Why the other options are incorrect

A. Project management plan – This is usually not yet fully developed; it is an output of planning processes, not an input to the cost management plan.

C. Cost estimates – Created after the cost management plan, not before.

D. Lessons learned – Helpful as organizational process assets, but not a primary input for preparing the cost management plan.
upvoted 1 times
...
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10