Exam CAPM Topic 1 Question 457 Discussion
Actual exam question for PMI's CAPM exam
Question #: 457
Topic #: 1
Question #: 457
Topic #: 1
Which of the following is used as an input to prepare a cost management plan?
Suggested Answer: A Vote an answer
by daccache.anthony at Mar 06, 2026, 01:08 AM
0
0
0
10
Comments
daccache.anthony
2026-03-06 01:08:10✅ B. Expert judgment
Explanation
When preparing a Cost Management Plan, one of the key inputs is expert judgment.
Experts provide knowledge and experience on estimating, budgeting, cost control methods, and applicable standards.
This input helps define:
How costs will be planned, structured, and controlled
Units of measure, accuracy levels, and reporting formats
Why the other options are incorrect
A. Project management plan – This is usually not yet fully developed; it is an output of planning processes, not an input to the cost management plan.
C. Cost estimates – Created after the cost management plan, not before.
D. Lessons learned – Helpful as organizational process assets, but not a primary input for preparing the cost management plan.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).