Exam PMP Topic 2 Question 1077 Discussion

Actual exam question for PMI's PMP exam
Question #: 1077
Topic #: 2
A project manager is in the process of closing out a project and has been asked by the project management office (PMO) to confirm that the transfer of knowledge to the operations team for support operations has been successfully completed. Which technique should the project manager apply to verify the knowledge transfer?

Suggested Answer: D Vote an answer

Expert judgment is a technique often used in project management to assess situations, make decisions, and resolve issues based on the knowledge and experience of experts. In the context of verifying knowledge transfer, expert judgment can be applied by consulting with individuals who have expertise in the subject matter of the knowledge transferred and the process of knowledge transfer itself. These experts can evaluate whether the knowledge has been comprehensively communicated and understood by the operations team. This approach aligns with the PMBOKGuide's principles, which recognize expert judgment as a valuable tool for project managers in various project management processes1.
References: The answer is supported by the principles found in the PMBOKGuide and the Professional in Business Analysis Reference Materials provided by PMI21.

by Parker at Nov 14, 2024, 05:58 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
adewumiwemimo20
2026-05-24 23:20:31
Best to use an SME (Subject Matter Expert) to confirm
upvoted 1 times
...