Exam PMP Topic 2 Question 1047 Discussion

Actual exam question for PMI's PMP exam
Question #: 1047
Topic #: 2
A project's cost performance index (CPI) and schedule performance index (SPI) are both greater than 1.0. The project manager decreases inputs to maintain the schedule. During this process, what remains unchanged?

Suggested Answer: A Vote an answer

by Noah at Apr 07, 2024, 03:26 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10