During a Stage 1 audit, the EMS Manager asks that the audit includes coverage of a new storage site on the other side of town that they have taken over since the application was made.
Which two of the following actions should the auditor take?
Which two of the following actions should the auditor take?
Suggested Answer: C,F Vote an answer
According to ISO/IEC 17021-1:2015 Clause 9.2.2 and 9.3.1:
Scope changes may be accommodated during the certification process, but proper evaluation is required.
The auditor should:
Confirm whether the EMS has been extended to cover the new site (C).
Inform that scope expansion needs to follow formal procedures through the certification body (F).
Simply including the new site without evaluation (A) is incorrect.
The audit plan can be adjusted, but full reassessment (D) is unnecessary unless significant issues arise.
Reference: ISO/IEC 17021-1:2015 Clause 9.2.2, 9.3.1; ISO 14001 Lead Auditor Course Guide.
Scope changes may be accommodated during the certification process, but proper evaluation is required.
The auditor should:
Confirm whether the EMS has been extended to cover the new site (C).
Inform that scope expansion needs to follow formal procedures through the certification body (F).
Simply including the new site without evaluation (A) is incorrect.
The audit plan can be adjusted, but full reassessment (D) is unnecessary unless significant issues arise.
Reference: ISO/IEC 17021-1:2015 Clause 9.2.2, 9.3.1; ISO 14001 Lead Auditor Course Guide.
by Reginald at Nov 05, 2025, 08:53 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).