Exam ISO-45001-Lead-Auditor Topic 1 Question 16 Discussion

Actual exam question for PECB's ISO-45001-Lead-Auditor exam
Question #: 16
Topic #: 1
Out of the following, which is not the Part of PDCA cycle ISO 45001? Select the correct option, and then select Submit.

Suggested Answer: C Vote an answer

The PDCA cycle (Plan-Do-Check-Act) is a core framework in ISO 45001 for continual improvement of the OH&S management system. An Environmental Management Program is part of ISO 14001 (Environmental Management System) and not ISO 45001.
Analysis of Options:
A . Treatment of Risks:
Correct. Risk treatment is part of the Plan phase.
B . OHSMS Policy:
Correct. The policy is developed in the Plan phase.
C . Environment Management Program:
Incorrect. This is outside the scope of ISO 45001 and relates to ISO 14001.
D . Analyzing OHSMS Performance:
Correct. Performance analysis is part of the Check phase.
ISO Reference:
Clause 0.3: PDCA framework in ISO 45001.

by Gloria at Jul 26, 2025, 12:53 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10