Exam ISO-45001-Lead-Auditor Topic 1 Question 16 Discussion
Actual exam question for PECB's ISO-45001-Lead-Auditor exam
Question #: 16
Topic #: 1
Question #: 16
Topic #: 1
Out of the following, which is not the Part of PDCA cycle ISO 45001? Select the correct option, and then select Submit.
Suggested Answer: C Vote an answer
The PDCA cycle (Plan-Do-Check-Act) is a core framework in ISO 45001 for continual improvement of the OH&S management system. An Environmental Management Program is part of ISO 14001 (Environmental Management System) and not ISO 45001.
Analysis of Options:
A . Treatment of Risks:
Correct. Risk treatment is part of the Plan phase.
B . OHSMS Policy:
Correct. The policy is developed in the Plan phase.
C . Environment Management Program:
Incorrect. This is outside the scope of ISO 45001 and relates to ISO 14001.
D . Analyzing OHSMS Performance:
Correct. Performance analysis is part of the Check phase.
ISO Reference:
Clause 0.3: PDCA framework in ISO 45001.
Analysis of Options:
A . Treatment of Risks:
Correct. Risk treatment is part of the Plan phase.
B . OHSMS Policy:
Correct. The policy is developed in the Plan phase.
C . Environment Management Program:
Incorrect. This is outside the scope of ISO 45001 and relates to ISO 14001.
D . Analyzing OHSMS Performance:
Correct. Performance analysis is part of the Check phase.
ISO Reference:
Clause 0.3: PDCA framework in ISO 45001.
by Gloria at Jul 26, 2025, 12:53 PM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.