Question #: 59
Topic #: 1
Question #: 59
Topic #: 1
While trying to upgrade AOS in a cluster, a consultant receives a warning message that there are two powered-on VMs that need to be powered off for the upgrade to proceed.
What would cause this warning to be issued?
What would cause this warning to be issued?
Suggested Answer: B Vote an answer
The warning message about powering off VMs during an AOS upgrade in a two-node cluster is issued because, in smaller clusters such as two-node configurations, resource availability and redundancy are limited.
To safely perform an upgrade without risking service disruption, the VMs need to be powered down to free up resources and ensure that there is sufficient capacity to handle the cluster operations during the upgrade process.References: Nutanix Bible, NCS-Core 6.8 course content, and Nutanix upgrade best practices.
To safely perform an upgrade without risking service disruption, the VMs need to be powered down to free up resources and ensure that there is sufficient capacity to handle the cluster operations during the upgrade process.References: Nutanix Bible, NCS-Core 6.8 course content, and Nutanix upgrade best practices.
by Donald at Jul 28, 2025, 12:45 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).