According to ATA owner-architect agreements, who is responsible for the cost of evaluating significant substitutions proposed by the contractor, subcontractors, or suppliers and the cost of making subsequent revisions to drawings, specifications, and other documentation?
Correct Answer: C
Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
After construction begins, an owner asks the architect to select a different roof material. The architect wants to manage the risk associated with this change.
Correct Answer: A
Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
A new restaurant design must incorporate specific light fixtures to meet the franchise requirements. The owner conveys this to the architect, who must make sure that prospective bidders do not overlook specific fixtures.
Which method should the architect use during the construction documents phase?
Which method should the architect use during the construction documents phase?
Correct Answer: B
Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
Who is responsible for verifying the accuracy of the contractor's payment application?
Correct Answer: A
Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
During the CD phase, it is discovered that the owner's food service consultant made a mistake that results in the owner asking the architect to revise the design.
How should the architect proceed?
How should the architect proceed?
Correct Answer: B
Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
Subsequent to the preparation of construction documents, prior to permitting, the enactment of codes or laws requires changes to the project.
Which of the following should occur?
Which of the following should occur?
Correct Answer: D
Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
Near the end of a routine job site visit, the architect begins to assemble notes. The owner's representative then arrives on site unexpectedly. The architect, owner's representative, and contractor discuss and resolve several outstanding project issues. The architect begins writing correspondence to distribute to the project team when the architect returns to the office.
In addition to a Meeting Record, which of the following documents should the architect create?
In addition to a Meeting Record, which of the following documents should the architect create?
Correct Answer: B
Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
The Integrated Project Delivery (IPD) method is used for a new football stadium project in an urban downtown area. After completing 60% implementation documents, the owner requests a digital scoreboard that is 20% larger than previously specified. The architect is concerned that the larger scoreboard will exceed the height limitations dictated by the city. The IPD team will conduct a constructability review and evaluate the modification of the scoreboard. Including the architect, which members of the IPD team are required to participate in the constructability review?
Correct Answer: B
Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).