Your project has a part-time resource who works 4 hours a day from Monday through Thursday. You need to ensure that your project plan accommodates the part-time resource. What should you do?
Correct Answer: D
Vote an answer
You manage several projects. Each project has shared resources and work distribution. You need to ensure that you can adjust the workload for specific resources used across multiple project schedules. What should you do?
Correct Answer: A
Vote an answer
You have a list of tasks in Microsoft Excel 2010. You need to create a Microsoft Project 2010 schedule that maintains the order of the tasks. Which two actions could you perform? (Each correct answer presents a complete solution. Choose two.)
Correct Answer: C,D
Vote an answer
You need to be able to send the custom Quick Access Toolbar to all users. What should you do?
Correct Answer: C
Vote an answer
You use Project Professional 2010 to manage a software development project as shown in the exhibit. (Click the Exhibit button.)

You need to cancel the Develop prototype based on functional specifications task. You also need to retain all the information from the task. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)

You need to cancel the Develop prototype based on functional specifications task. You also need to retain all the information from the task. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
Correct Answer: A,E
Vote an answer
You add a new summary task and detailed tasks to an existing project. You save the changes as Baseline2. You discover that Baseline2 only displays work hours for detailed tasks. You need to ensure that Baselinez displays work hours in the new summary task. What should you do?
Correct Answer: C
Vote an answer
Your project schedule contains both Work and Material resources. The resources are assigned to tasks and are of either the committed or proposed booking type. You need to ensure that the project does not contain over-allocated resources. Which feature should you use?
Correct Answer: A
Vote an answer