Exam ITIL-DSV Topic 1 Question 74 Discussion

Actual exam question for ITIL's ITIL-DSV exam
Question #: 74
Topic #: 1
A customer is retiring a service and has terminated the contract for the service with the service provider. The service provider will continue to deliver other services to the customer.
Which activity should the service provider include in the plans to offboard the service?

Suggested Answer: C Vote an answer

When offboarding a service, the service provider should include "Identifying and making requests for outstanding payments for the service." ITIL 4 specifies that offboarding activities should ensure that all financial and contractual obligations are settled before the service is fully retired. This includes resolving any outstanding payments, finalizing documentation, and ensuring a smooth transition for ongoing services.

by Prudence at Aug 24, 2024, 07:27 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10