You have been asked to implement formal reviews at your company. From the list below, what are the correct characteristics of a formal review?
a. Entry and exit criteria have been defined.
b. Checklists created to be used by all reviewers.
c. Consistency with current project plan is checked.
d. Metrics on effectiveness will be gathered.
e. The review will be moderated by a lead auditor.
a. Entry and exit criteria have been defined.
b. Checklists created to be used by all reviewers.
c. Consistency with current project plan is checked.
d. Metrics on effectiveness will be gathered.
e. The review will be moderated by a lead auditor.
Correct Answer: A
Vote an answer
What is a "depth-first" risk-based testing technique?
Correct Answer: B
Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
Your company just won a contract to create a new sales application and has committed to a very aggressive delivery timeline. Due to the quick turnaround your primary stakeholder wants to be heavily involved in the design and is very anxious to see the outcome. Because of this, your company has decided to use a spiral development approach. You have a defined test policy and typically use an analytical approach to testing, however, this approach will not work with the development approach.
What test strategy should be utilized?
What test strategy should be utilized?
Correct Answer: A
Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
You are planning the testing for an emergency product update required to correct a serious security issue and to improve system maintainability of a key product in your company's catalogue. It has been estimated that the historical cost to the company for the security issue in this system has been $375,000.
In the last year a total of 10 reported "live' incidents were reported, resulting in a total external failure cost of S110.000 to correct.
The cost of prevention for this project has been estimated as $78,500 and from the development you have learned that the average cost of detection was $1,250 and the average cost of internal failure was $7,450 Which one of the following statements about cost of quality is TRUE? SELECT ONE OPTION
In the last year a total of 10 reported "live' incidents were reported, resulting in a total external failure cost of S110.000 to correct.
The cost of prevention for this project has been estimated as $78,500 and from the development you have learned that the average cost of detection was $1,250 and the average cost of internal failure was $7,450 Which one of the following statements about cost of quality is TRUE? SELECT ONE OPTION
Correct Answer: C
Vote an answer
Referring to SCENARIO 2 It has been agreed that Project 1 will be delivered using an Agile approach, with user stories delivered across three sprints, each lasting 4 weeks. The programme manager is concerned about RISK 3 and wants the Master Test Plan to specify an effective test process improvement approach.
Which of the following is the best test process improvement approach for Project 1 ? SELECT ONE OPTION
Which of the following is the best test process improvement approach for Project 1 ? SELECT ONE OPTION
Correct Answer: D
Vote an answer
'Safe as Houses' is a company that specialises in home security software, including alarm systems, surveillance cameras and other forms of deterrence.
It is currently developing the software for a device which simulates an active television, producing sound and light images that suggest someone is home watching the television. 'Safe as Houses' recently won a lucrative contract to supply the software to Smart Alarms', who will be manufacturing the hardware devices Sound will be created using actual television and film archives, licensed through a third-party supplier, 'Silver Sound Ltd'. A user interface will be developed in house to allow the customer to choose sound tracks.
The software will be delivered as a programme of work, consisting of three projects. Project 1 will develop the software for the light images. Project 2 will develop the sound system and Project 3 will integrate the two using hardware prototypes supplied from 'Smart Alarms'. The programme will conclude with 'Smart Alarms' performing User Acceptance testing in usability labs.
The 'Safe as Houses' test team has experience in testing alarm and surveillance systems but lacks experience in testing light imagery software. The organisational test policy includes the following objectives:
1 Exploratory testing should be used to augment more formal, structured testing within constraints of time and budget
2. Test automation tools should be purchased and employed to maximise the breadth and efficiency of regression testing The Programme risk register currently includes the following risks:
RISK1 Working prototypes will be delivered late to the integration test environments RISK 2 A delay in signing the contract with 'Silver Sound Ltd' will impact the programme schedule RISK 3 Inexperience in testing light imagery software will cause major defects to be missed RISK 4 The user interface software for the sound systems will be delivered late into testing Refer to SCENARIO 2 - The IT Director for 'Safe as Houses' is recruiting a Programme Test Manager and has been provided with a skills matrix for four prospective candidates. The matrix shows the skill level (5 being highest. 1 lowest) for each candidate:

Consider which of these skills are key for a Programme Test manager in this scenario. Based on these, which candidate would be the most suitable?
SELECT ONE OPTION
It is currently developing the software for a device which simulates an active television, producing sound and light images that suggest someone is home watching the television. 'Safe as Houses' recently won a lucrative contract to supply the software to Smart Alarms', who will be manufacturing the hardware devices Sound will be created using actual television and film archives, licensed through a third-party supplier, 'Silver Sound Ltd'. A user interface will be developed in house to allow the customer to choose sound tracks.
The software will be delivered as a programme of work, consisting of three projects. Project 1 will develop the software for the light images. Project 2 will develop the sound system and Project 3 will integrate the two using hardware prototypes supplied from 'Smart Alarms'. The programme will conclude with 'Smart Alarms' performing User Acceptance testing in usability labs.
The 'Safe as Houses' test team has experience in testing alarm and surveillance systems but lacks experience in testing light imagery software. The organisational test policy includes the following objectives:
1 Exploratory testing should be used to augment more formal, structured testing within constraints of time and budget
2. Test automation tools should be purchased and employed to maximise the breadth and efficiency of regression testing The Programme risk register currently includes the following risks:
RISK1 Working prototypes will be delivered late to the integration test environments RISK 2 A delay in signing the contract with 'Silver Sound Ltd' will impact the programme schedule RISK 3 Inexperience in testing light imagery software will cause major defects to be missed RISK 4 The user interface software for the sound systems will be delivered late into testing Refer to SCENARIO 2 - The IT Director for 'Safe as Houses' is recruiting a Programme Test Manager and has been provided with a skills matrix for four prospective candidates. The matrix shows the skill level (5 being highest. 1 lowest) for each candidate:

Consider which of these skills are key for a Programme Test manager in this scenario. Based on these, which candidate would be the most suitable?
SELECT ONE OPTION
Correct Answer: D
Vote an answer
You plan to use a heavyweight approach to risk-based testing on a safety-critical system and have the following information available for each documented product risk:
* The estimated cost of testing the risk
* How likely a failure would arise for the risk item
* How much the failure would cost, in terms of lossWhich technique would be MOST suitable?
* The estimated cost of testing the risk
* How likely a failure would arise for the risk item
* How much the failure would cost, in terms of lossWhich technique would be MOST suitable?
Correct Answer: D
Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
Your current project is delivering a warehouse management system for use in distribution centres, you are writing a test plan to address acceptance testing. You need to determine which stakeholders would be interested in receiving regular reports covering the progress of test execution against agreed schedule and budget. Which roles would be MOST interested in these reports?
Correct Answer: A,B,E
Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
You are testing a new product that will turn on the windshield wipers of a car when the sensors detect there is moisture on the windshield. Depending on the information returned from the sensors, the wipers will be turned on at one of the following speeds: slow intermittent, medium intermittent, fast intermittent, slow constant, medium constant, fast constant. Your team has identified the following test condition:
Test Condition 1.1.1 - Verify that the windshield wipers can go from slow constant to fast constant speed when the amount of moisture increases appropriately.
Your team has defined the following steps for a test case for this test condition:
1. Set the moisture sensor to request slow constant
2. Increase the moisture to set the sensor to request fast constant
3. Verify that the wipers respond with fast constant speed
Given this information, which of the following statements is correct? [2]
Test Condition 1.1.1 - Verify that the windshield wipers can go from slow constant to fast constant speed when the amount of moisture increases appropriately.
Your team has defined the following steps for a test case for this test condition:
1. Set the moisture sensor to request slow constant
2. Increase the moisture to set the sensor to request fast constant
3. Verify that the wipers respond with fast constant speed
Given this information, which of the following statements is correct? [2]
Correct Answer: C
Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
It is now the last day of the second iteration and the team has been consistently underestimating the time needed. They estimate intuitively rather than using estimation techniques.
Which two estimation techniques would be BEST for the team in this scenario?
Which two estimation techniques would be BEST for the team in this scenario?
Correct Answer: B,D
Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).
Which two items are MOST relevant for inclusion in your tool selection plan for functional test automation in Agile?
Correct Answer: A,B
Vote an answer
Explanation: Only visible for ExamDiscuss members. You can sign-up / login (it's free).