Exam CCBA Topic 4 Question 352 Discussion
Actual exam question for IIBA's CCBA exam
Question #: 352
Topic #: 4
Question #: 352
Topic #: 4
The initial high-level listing of requirements in a change-driven approach is also known as what?
Suggested Answer: A Vote an answer
Explanation
The initial high-level listing of requirements in a change-driven approach is also known as requirements envisioning.
Answer D is incorrect. The project scope defines all of the required work to satisfy the requirements of the project.
Answer C is incorrect. The product scope defines all of the features and functions of the thing, solution, or service the project or organization will create.
Answer B is incorrect. Requirements foundation is not a valid term for business analysis.
The initial high-level listing of requirements in a change-driven approach is also known as requirements envisioning.
Answer D is incorrect. The project scope defines all of the required work to satisfy the requirements of the project.
Answer C is incorrect. The product scope defines all of the features and functions of the thing, solution, or service the project or organization will create.
Answer B is incorrect. Requirements foundation is not a valid term for business analysis.
by Armand at Sep 14, 2025, 10:55 PM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).