Exam CCBA Topic 5 Question 126 Discussion
Actual exam question for IIBA's CCBA exam
Question #: 126
Topic #: 5
Question #: 126
Topic #: 5
A software company wants to make a gradual change from its traditional way of developing requirements to a more adaptive approach. A business analyst (BA) is hired to quantify the probability that the solution will meet the company's needs and assess the relevant risks. Which element of risk assessment does the BA need to consider?
Suggested Answer: C Vote an answer
Comprehensive and Detailed Risk tolerancedetermineshow much uncertainty the company is willing to accept in shifting to an adaptive approach.
BABOK Guide (Chapter 10.37 - Risk Analysis and Management)explains that organizations must evaluate theirwillingness to embrace changes and uncertainty in new methodologies.
Issue management (Option A)addresses risks reactively rather than proactively.
Negative impact to value (Option B)considers outcomes but not tolerance.
Positive evaluation results (Option D)do not measure risk acceptance.
BABOK Guide (Chapter 10.37 - Risk Analysis and Management)explains that organizations must evaluate theirwillingness to embrace changes and uncertainty in new methodologies.
Issue management (Option A)addresses risks reactively rather than proactively.
Negative impact to value (Option B)considers outcomes but not tolerance.
Positive evaluation results (Option D)do not measure risk acceptance.
by Celeste at Jul 30, 2025, 02:25 AM