Exam CBAP Topic 3 Question 41 Discussion

Actual exam question for IIBA's CBAP exam
Question #: 41
Topic #: 3
The, an output of the define scope process, does document the process and criteria for accepting completed products.

Suggested Answer: C Vote an answer

Explanation
The project scope statement, an output of the define scope process, does document the process and criteria for accepting completed products. The project scope statement is a detailed description of the project scope, which includes the project objectives, deliverables, requirements, boundaries, assumptions, and constraints. The project scope statement also defines the acceptance criteria, which are the standards or measures that must be met or satisfied by the products, services, or results of the project. The acceptance criteria help to ensure that the customer's needs and expectations are met and that the project quality is achieved. The project scope statement is a key input for developing the work breakdown structure, the project schedule, the project budget, and the project quality plan. References: [IIBA BABOK Guide v3], section 5.1.2, page 162; [CBAP / CCBA Certified Business Analysis Study Guide], chapter 6, page 233; CBAP Sample Questions, question 253.

by Leopold at Dec 27, 2024, 12:51 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.