Which type of equipment maintenance program can cause the most unplanned downtime and least predictable costs?

Suggested Answer: C Vote an answer

Corrective maintenance(also called "reactive maintenance") occursonly after equipment fails, leading to:
* Unplanned downtimethat disrupts operations.
* Higher repair costsdue to emergency fixes.
* Shorter equipment lifespanbecause maintenance is delayed.
Preventive (A) and predictive (B) maintenancereduce downtime by scheduling repairs before failure.24- hour (D)is not a recognized maintenance strategy.

by Andy at Apr 14, 2025, 11:59 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10