Exam 312-38 Topic 10 Question 229 Discussion

Actual exam question for EC-COUNCIL's 312-38 exam
Question #: 229
Topic #: 10
Management decides to implement a risk management system to reduce and maintain the organization's risk at an acceptable level. Which of the following is the correct order in the risk management phase?

Suggested Answer: A Vote an answer

The correct order in the risk management phase starts with Risk Identification, where potential business risks are determined. This is followed by Risk Assessment, which involves analyzing and prioritizing the identified risks. Next is Risk Treatment, where plans are made to mitigate the risks. Finally, Risk Monitoring & Review is conducted to oversee the risk management process and make necessary adjustments. This sequence ensures a structured and effective approach to managing risks within an organization. Reference: The sequence aligns with the widely recognized ISO 31000 risk management standard, which outlines these core steps in managing risks123.

by Jim at Jul 14, 2025, 11:55 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10