Exam SY0-701 Topic 4 Question 682 Discussion

Actual exam question for CompTIA's SY0-701 exam
Question #: 682
Topic #: 4
A company makes a change during the appropriate change window, but the unsuccessful change extends beyond the scheduled time and impacts customers. Which of the following would prevent this from reoccurring?

Suggested Answer: D Vote an answer

A backout plan provides a documented procedure to revert or undo a change if it fails or causes issues, helping to restore the environment quickly and prevent extended downtime. Having a backout plan in place minimizes impact during failed changes.
User notification (A) informs users but does not prevent failures. Change approval (B) and risk analysis (C) occur before the change and cannot fix issues after failure.
Backout planning is a best practice in Change Management covered in Security Program Management#6:
Chapter 16 CompTIA Security+ Study Guide#

by Abbott at Dec 09, 2025, 09:48 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10