Exam SY0-701 Topic 1 Question 314 Discussion
Actual exam question for CompTIA's SY0-701 exam
Question #: 314
Topic #: 1
Question #: 314
Topic #: 1
Which of the following steps in the risk management process involves establishing the scope and potential risks involved with a project?
Suggested Answer: B Vote an answer
Risk identificationis the first step in the risk management process, where potential threats and vulnerabilities are analyzed to understand their impact on an organization. This includesidentifying assets, evaluating threats, and assessing potential vulnerabilities.
* Risk mitigation: Reducing risk by implementing controls.
* Risk treatment: Determining how to handle identified risks.
* Risk monitoring and review: Ongoing evaluation of risk controls.
* Risk mitigation: Reducing risk by implementing controls.
* Risk treatment: Determining how to handle identified risks.
* Risk monitoring and review: Ongoing evaluation of risk controls.
by Werner at Jun 30, 2025, 02:57 AM