Question #: 314
Topic #: 1
Which of the following steps in the risk management process involves establishing the scope and potential risks involved with a project?

Suggested Answer: B Vote an answer

Risk identificationis the first step in the risk management process, where potential threats and vulnerabilities are analyzed to understand their impact on an organization. This includesidentifying assets, evaluating threats, and assessing potential vulnerabilities.
* Risk mitigation: Reducing risk by implementing controls.
* Risk treatment: Determining how to handle identified risks.
* Risk monitoring and review: Ongoing evaluation of risk controls.

by Werner at Jun 30, 2025, 02:57 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10