A site is considered a warm site when it:
Suggested Answer: C Vote an answer
A warm site is a backup site that has some of the necessary hardware, software, and network resources to resume operations, but not all of them. A warm site requires some time and effort to become fully operational.
A warm site is different from a cold site, which has minimal or no resources, and a hot site, which has all the resources and is ready to take over immediately.
References: CompTIA Server+ Study Guide, Chapter 10: Disaster Recovery, page 403.
A warm site is different from a cold site, which has minimal or no resources, and a hot site, which has all the resources and is ready to take over immediately.
References: CompTIA Server+ Study Guide, Chapter 10: Disaster Recovery, page 403.
by Thomas at Mar 14, 2025, 07:37 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).