Exam SK0-005 Topic 2 Question 381 Discussion

Actual exam question for CompTIA's SK0-005 exam
Question #: 381
Topic #: 2
A site is considered a warm site when it:

Suggested Answer: C Vote an answer

A warm site is a backup site that has some of the necessary hardware, software, and network resources to resume operations, but not all of them. A warm site requires some time and effort to become fully operational.
A warm site is different from a cold site, which has minimal or no resources, and a hot site, which has all the resources and is ready to take over immediately.
References: CompTIA Server+ Study Guide, Chapter 10: Disaster Recovery, page 403.

by Thomas at Mar 14, 2025, 07:37 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10