Exam PK0-005 Topic 1 Question 96 Discussion
Actual exam question for CompTIA's PK0-005 exam
Question #: 96
Topic #: 1
Question #: 96
Topic #: 1
A risk management team for a software project decided to outsource the development of a specific portion of a
system due to a lack of internal resources. Which of the following risk responses does this demonstrate?
system due to a lack of internal resources. Which of the following risk responses does this demonstrate?
Suggested Answer: B Vote an answer
Outsourcing the development of a system component due to a lack of internal resources is a risk response
strategy known as 'transfer.' This approach shifts the risk to a third party who will now be responsible for
managing that portion of the project. It is commonly used when an organization does not have the expertise or
capacity to handle specific risks internally.
References = The answer is based on standard project management practices and the typical use of risk
response strategies in the field. For detailed information, please refer to the CompTIA Project+ Study Guide
and other official CompTIA resources.
strategy known as 'transfer.' This approach shifts the risk to a third party who will now be responsible for
managing that portion of the project. It is commonly used when an organization does not have the expertise or
capacity to handle specific risks internally.
References = The answer is based on standard project management practices and the typical use of risk
response strategies in the field. For detailed information, please refer to the CompTIA Project+ Study Guide
and other official CompTIA resources.
by Jay at Sep 18, 2024, 02:36 PM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).