Free L4M8 Questions for CIPS Procurement and Supply in Practice L4M8 Exam as PDF & Practice Test Engine
Explain the difference between bonded and forced labor.
Correct Answer:
See the answer in explanation.
Explanation:
Bonded labour and forced labour are among the five types of modern slavery which is against ethical and responsible sourcing.
Bonded labour also known as debt bondage, this is an individual's promise to provide services through exploitation as repayment, or part of them, of a debt or other obligation whereas forced labour is work that people are forced to do with the heat of punishment if it is not carried out.
(Correct)
Explanation:
Bonded labour and forced labour are among the five types of modern slavery which is against ethical and responsible sourcing.
Bonded labour also known as debt bondage, this is an individual's promise to provide services through exploitation as repayment, or part of them, of a debt or other obligation whereas forced labour is work that people are forced to do with the heat of punishment if it is not carried out.
(Correct)
What is CSR policy?
Correct Answer:
See the answer in explanation.
Explanation:
Corporate Social responsibility (CSR) policies state how organizations aim to contribute towards the community and how an organization portrays itself towards social impacts.
Explanation:
Corporate Social responsibility (CSR) policies state how organizations aim to contribute towards the community and how an organization portrays itself towards social impacts.
What are advantages and disadvantages of the two types of specifications?
Correct Answer:
See the answer in explanation.
Explanation:
Ones the need is understood, the procurement professional develops the specifications while working together with stakeholders and colleagues to ensure that the final design is fit for purposes that it meets the generated need.
Specification can be focus on performance or conformance.
Performance specification states what the product or service must do or how it should perform but leave the supplier the freedom to achieve this, however they wish.
Performance specification brings the following advantages; it allows supplier innovation, promote competition in the market place, shorter document, quick to prepare. The disadvantage of perfor-mance specification is that buyers may not know exactly what they will be getting.
Conformance specification gives clear instructions to the supplier about what is required and how it should be achieved. Examples of conformance specifications are chemical formulae, recipes and technical drawings.
Conformance specification specifies which standards a requirement must meet or exceed. The advantage of using it is; buyers know exactly what they will get. It has the following disadvantages; the buyer bears the risk, it does not encourage supplier to innovate, take longer and complex documentation.
* Refer to the question column for response
Explanation:
Ones the need is understood, the procurement professional develops the specifications while working together with stakeholders and colleagues to ensure that the final design is fit for purposes that it meets the generated need.
Specification can be focus on performance or conformance.
Performance specification states what the product or service must do or how it should perform but leave the supplier the freedom to achieve this, however they wish.
Performance specification brings the following advantages; it allows supplier innovation, promote competition in the market place, shorter document, quick to prepare. The disadvantage of perfor-mance specification is that buyers may not know exactly what they will be getting.
Conformance specification gives clear instructions to the supplier about what is required and how it should be achieved. Examples of conformance specifications are chemical formulae, recipes and technical drawings.
Conformance specification specifies which standards a requirement must meet or exceed. The advantage of using it is; buyers know exactly what they will get. It has the following disadvantages; the buyer bears the risk, it does not encourage supplier to innovate, take longer and complex documentation.
* Refer to the question column for response
What are the four stages of decommissioning?
Correct Answer:
See the answer in explanation.
Explanation:
When a fixed asset reaches the end of its life, it requires decommissioning before reconditioning or disposal.
Decommissioning is to observe all the safety measures and technical procedures and stop active machinery or an asset from operation (example gas plan, generator, transformer etc.
Decommissioning process include the following aspect
1) Preparation: Plan the process
2) Dismantle: Take the asset apart and remove hazardous waste
3) Processing: make safe any hazardous waste
4) Disposal: Ensure paper work is received to confirm removal and disposal
* Refer to the question column for response
Explanation:
When a fixed asset reaches the end of its life, it requires decommissioning before reconditioning or disposal.
Decommissioning is to observe all the safety measures and technical procedures and stop active machinery or an asset from operation (example gas plan, generator, transformer etc.
Decommissioning process include the following aspect
1) Preparation: Plan the process
2) Dismantle: Take the asset apart and remove hazardous waste
3) Processing: make safe any hazardous waste
4) Disposal: Ensure paper work is received to confirm removal and disposal
* Refer to the question column for response
Why do some specifications need to adapt?
Correct Answer:
See the answer in explanation.
Explanation:
Specification is a detailed description of what is required or needed. Due to certain reasons, needs sometimes increase in importance or lose their essence, therefore speci-fications need to adapt and develop to reflect the changing requirements of the con-sumer and also to comply with regulations and legislatures as this are amended.
Standard, regulations and legislation are continually evolving and new updated versions of existing guideline, as well as completely new initiatives one being released.
Explanation:
Specification is a detailed description of what is required or needed. Due to certain reasons, needs sometimes increase in importance or lose their essence, therefore speci-fications need to adapt and develop to reflect the changing requirements of the con-sumer and also to comply with regulations and legislatures as this are amended.
Standard, regulations and legislation are continually evolving and new updated versions of existing guideline, as well as completely new initiatives one being released.
Explain with examples three differences between offers and invitation to treat.
Correct Answer:
See the answer in explanation.
Explanation:
An offer is created when one party communicates to another or to multiple parties that they wish to enter into a legal binding agreement in accordance with the terms stated, for example; a company in promotion advertising for buyers to buy one and get one free, an offer is a buying organization communicating to a supplier to supply X number of goods and be paid x amount upon delivery at company premises, an offer is when a football club proposes to pay X amount to a player if agrees to play for them for a month. An offer can be legally banded if accepted, whereas invitation to treat does not. An invitation to treat is just an invitation from one party to another to begin negotiations with the intention of creating an offer. If an offer is made without stating terms, this becomes an invitation to treat, for example, an invitation to treat is when a pharmacy displays a drug in its shelf. An invitation to treat can be linked to a request a buyer send to suppliers asking them for specific information.
Explanation:
An offer is created when one party communicates to another or to multiple parties that they wish to enter into a legal binding agreement in accordance with the terms stated, for example; a company in promotion advertising for buyers to buy one and get one free, an offer is a buying organization communicating to a supplier to supply X number of goods and be paid x amount upon delivery at company premises, an offer is when a football club proposes to pay X amount to a player if agrees to play for them for a month. An offer can be legally banded if accepted, whereas invitation to treat does not. An invitation to treat is just an invitation from one party to another to begin negotiations with the intention of creating an offer. If an offer is made without stating terms, this becomes an invitation to treat, for example, an invitation to treat is when a pharmacy displays a drug in its shelf. An invitation to treat can be linked to a request a buyer send to suppliers asking them for specific information.
When benchmarking what other factors, apart from price should be considered to find the total cost of acquisition?
Correct Answer:
See the answer in explanation.
Explanation:
When evaluating potential suppliers, procurement professionals can carry out bench-marking. Benchmarking is the process of comparing a function, a process performance with another which is best in-class.
Other factors, apart from price that can be considered to find the total cost of acquisi-tion include the product or service quality, lead time, supplier culture, its environmental awareness and sustainability.
Explanation:
When evaluating potential suppliers, procurement professionals can carry out bench-marking. Benchmarking is the process of comparing a function, a process performance with another which is best in-class.
Other factors, apart from price that can be considered to find the total cost of acquisi-tion include the product or service quality, lead time, supplier culture, its environmental awareness and sustainability.
Describe three types of fraud that could occur within the supply chain of an organization with which you are familiar.
Correct Answer:
See the answer in explanation.
Explanation:
Fraud occurs when a person acts deliberately to secure monies from another party through dishonest method.
Within the supply chain of an organization, fraud can represent itself in the following ways:
1. Kickbacks: e.g. (commission given to a bribe taker for service perform)
2. Corrupt influence (e.g ordering more than what is required)
3. Collusion: (group of suppliers working together to submit multiple bids and split profit.
4. Bid Rigging (a contract is informally agreed with a chosen supplier prior to the official process
5. invoicing fraud
6. Substitution (submitting products that are below the required quality
7. False claims (files false document)
* Refer to the question column for response
Explanation:
Fraud occurs when a person acts deliberately to secure monies from another party through dishonest method.
Within the supply chain of an organization, fraud can represent itself in the following ways:
1. Kickbacks: e.g. (commission given to a bribe taker for service perform)
2. Corrupt influence (e.g ordering more than what is required)
3. Collusion: (group of suppliers working together to submit multiple bids and split profit.
4. Bid Rigging (a contract is informally agreed with a chosen supplier prior to the official process
5. invoicing fraud
6. Substitution (submitting products that are below the required quality
7. False claims (files false document)
* Refer to the question column for response
What are the five stages in Tuckman's team Development model?
Correct Answer:
See the answer in explanation.
Explanation:
Tuckman's team development model depicts from where a team is formed to the various stages they might experience before the end where the objective is achieved and these includes.
1) Forming: here they are just being put together
2) Storming: conflict and competition begin to arise
3) Norming: here agreement and consensus is reached as roles and responsibility is clear.
4) Perform: They start carrying out the roles and responsibility
5) Adjourning: Task is complete and they are discharged
* Refer to the question column for response
Explanation:
Tuckman's team development model depicts from where a team is formed to the various stages they might experience before the end where the objective is achieved and these includes.
1) Forming: here they are just being put together
2) Storming: conflict and competition begin to arise
3) Norming: here agreement and consensus is reached as roles and responsibility is clear.
4) Perform: They start carrying out the roles and responsibility
5) Adjourning: Task is complete and they are discharged
* Refer to the question column for response
What matrix helps to define how to manage stakeholders?
Correct Answer:
See the answer in explanation.
Explanation:
Stakeholders are individuals or organizations who are directly affected by a decision for example, community, shareholders, employees, suppliers, distributors, customers etc. stakeholders can be internal (employers, staffs), connected (such as suppliers, shareholders, financers and customers) external (Government, pressure groups, and community).
The matrix that helps define how to manage stakeholders is mendelow's stakeholders manage-ment matrix.
This matrix is based on the theory that the level of management stakeholders require depends on the level of their power and interest within the project or organization The matrix groups stakeholders in to four quadrants according to their power and interest and ad-vice how to manage them.
1) Low power - Low interest (minimum effort)
2) Low power - High interest (keep inform)
3) High power - Low interest (keep satisfied)
4) High power - high interest (manage closely)
Explanation:
Stakeholders are individuals or organizations who are directly affected by a decision for example, community, shareholders, employees, suppliers, distributors, customers etc. stakeholders can be internal (employers, staffs), connected (such as suppliers, shareholders, financers and customers) external (Government, pressure groups, and community).
The matrix that helps define how to manage stakeholders is mendelow's stakeholders manage-ment matrix.
This matrix is based on the theory that the level of management stakeholders require depends on the level of their power and interest within the project or organization The matrix groups stakeholders in to four quadrants according to their power and interest and ad-vice how to manage them.
1) Low power - Low interest (minimum effort)
2) Low power - High interest (keep inform)
3) High power - Low interest (keep satisfied)
4) High power - high interest (manage closely)
Which Incoterm applies here?
The supplier is responsible for delivering the goods directly onto the vessel that will transport them to their named destination. As soon as the goods are on the vessel, the risk transfers to the buyer
The supplier is responsible for delivering the goods directly onto the vessel that will transport them to their named destination. As soon as the goods are on the vessel, the risk transfers to the buyer
Correct Answer: B
Vote an answer
What happens in the public sector, regarding providing feedback?
Correct Answer:
See the answer in explanation.
Explanation:
A sector is an area of an industry, e.g., private, public or third sector.
A public sector is a sector of the economy that is owned, finance and run by the government. This sector is financed with tax payer's money. And therefore owe the general public an ethical explanation towards all investment and decision.
Once the supplier that is awarded the contract has accepted, the buyer can tell the unsuccessful bidders. This usually happens through email or letter. The public sector is more likely to give feedback to unsuccessful bidders and also have to respond to any stakeholders that request information on why a supplier is not successful.
Explanation:
A sector is an area of an industry, e.g., private, public or third sector.
A public sector is a sector of the economy that is owned, finance and run by the government. This sector is financed with tax payer's money. And therefore owe the general public an ethical explanation towards all investment and decision.
Once the supplier that is awarded the contract has accepted, the buyer can tell the unsuccessful bidders. This usually happens through email or letter. The public sector is more likely to give feedback to unsuccessful bidders and also have to respond to any stakeholders that request information on why a supplier is not successful.