Ramesh is an IT category manager within the UK's NHS and is responsible for the procurement of a new high-value network system. Ramesh has concluded that the use of a restricted tender is the most appropriate.
Which of the following statements is true for a restricted tender process?

Suggested Answer: B Vote an answer

Restricted tendering is a two-stage process: first, a pre-qualification stage to ensure only capable, compliant suppliers are invited; second, the issue of the ITT to that shortlist. This method is appropriate when requirements are complex, high-value, or where assurance of supplier competence is essential. It is not based solely on price and does not rely on limited supplier numbers but on filtering through qualification. This balances transparency and efficiency, avoiding wasteful evaluation of unsuitable suppliers while still maintaining competitive tension. CIPS L4M4 highlights that restricted tendering strengthens governance, improves efficiency, and ensures due diligence in supplier selection.
Reference: CIPS L4M4 Study Guide (v2), LO: "Implementation" - tendering methods (open, restricted, negotiated).

by Stev at May 10, 2026, 03:50 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10