Exam L5M2 Topic 3 Question 116 Discussion

Actual exam question for CIPS's L5M2 exam
Question #: 116
Topic #: 3
Which of the following FIDIC Contracts would be suitable for a contract for offshore wind projects?

Suggested Answer: D Vote an answer

Explanation
This is the Yellow Book. This is briefly mentioned on p.74 and can often be missed by students. There is a question in the exam about which type of FIDIC contract can be used for construction projects and this is NOT explained in the study guide - so here is a link to FIDIC so you can revise this before the exam:
https://fidic.org/sites/default/files/FIDIC_Suite_of_Contracts_0.pdf

by Stanley at Nov 20, 2025, 04:52 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10