During which stage of the procurement cycle would you remove suppliers that do not add value, or could pose a risk to the buying organisation?
Suggested Answer: B Vote an answer
At supplier selection stage, unsuitable suppliers should be removed (those that do not add value or pose a risk). At develop strategy stage you're not even looking at suppliers yet- you're just deciding what you need.
At contract award and asset management it's too late.
CIPS procurement cycle - Procurement Supply Cycle | CIPS
At contract award and asset management it's too late.
CIPS procurement cycle - Procurement Supply Cycle | CIPS
by Maurice at May 22, 2025, 04:58 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).