Exam L4M4 Topic 2 Question 136 Discussion

Actual exam question for CIPS's L4M4 exam
Question #: 136
Topic #: 2
During which stage of the procurement cycle would you remove suppliers that do not add value, or could pose a risk to the buying organisation?

Suggested Answer: B Vote an answer

At supplier selection stage, unsuitable suppliers should be removed (those that do not add value or pose a risk). At develop strategy stage you're not even looking at suppliers yet- you're just deciding what you need.
At contract award and asset management it's too late.
CIPS procurement cycle - Procurement Supply Cycle | CIPS

by Maurice at May 22, 2025, 04:58 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10