Exam CPIM-8.0 Topic 1 Question 488 Discussion
Actual exam question for APICS's CPIM-8.0 exam
Question #: 488
Topic #: 1
Question #: 488
Topic #: 1
For a process that is outside its upper control limit (UCL), which of the following techniques would best be used to return the process under control?
Suggested Answer: B Vote an answer
Plan-do-check-action (PDCA) is a technique that would best be used to return a process under control when it is outside its upper control limit (UCL). PDCA is a four-step cycle of continuous improvement that involves planning a change, implementing the change, checking the results, and acting on the findings. PDCA can help identify and eliminate the root causes of variation, improve the process performance, and prevent the recurrence of problems. PDCA is also known as the Deming cycle or the Shewhart cycle. References:
* Managing Supply Chain Operations, Chapter 9: Quality Management, Section 9.3: Quality Improvement, Subsection 9.3.1: Plan-Do-Check-Act Cycle
* CPIM Exam Content Manual, Module 8: Quality, Technology and Continuous Improvement, Section
8.2: Continuous Improvement, Subsection 8.2.1: Continuous Improvement Concepts, Subsubsection
8.2.1.1: Plan-Do-Check-Act Cycle
* Managing Supply Chain Operations, Chapter 9: Quality Management, Section 9.3: Quality Improvement, Subsection 9.3.1: Plan-Do-Check-Act Cycle
* CPIM Exam Content Manual, Module 8: Quality, Technology and Continuous Improvement, Section
8.2: Continuous Improvement, Subsection 8.2.1: Continuous Improvement Concepts, Subsubsection
8.2.1.1: Plan-Do-Check-Act Cycle
by Moses at Apr 12, 2026, 11:19 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).