Exam CAP Topic 23 Question 15 Discussion

Actual exam question for The SecOps Group's CAP exam
Question #: 15
Topic #: 23
Rob is the project manager of the IDLK Project for his company. This project has a budget of $5,600,000 and is expected to last 18 months. Rob has learned that a new law may affect how the project is allowed to proceed
- even though the organization has already invested over $750,000 in the project. What risk response is the most appropriate for this instance?

Suggested Answer: D Vote an answer

Section: Volume B

by Darlene at Jul 20, 2025, 04:00 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10